Spa-Style Master Bathroom
Most dated master bathrooms are not short on square footage — they are short on a layout that uses it. A large corner garden tub nobody has filled in a decade, a single vanity, and a cramped shower is an extremely common arrangement in valley homes built between the mid-eighties and the early two-thousands.
Reallocating that same footprint is usually the entire project. Give the shower the space the tub was wasting, and there is room for a genuine double vanity and clear circulation.

Scope of Work
- Full demolition to studs
- Reworked layout reallocating tub footprint to the shower
- Double vanity with dedicated storage
- Frameless glass walk-in shower with full waterproofing
- New tile to ceiling in the wet area
- Upgraded ventilation and moisture-rated lighting
Materials & Finishes
- Vanity
- Double, with drawer storage
- Shower
- Frameless glass walk-in
- Waterproofing
- Full membrane system behind tile
- Tile
- Large-format, run to ceiling in wet area
- Ventilation
- Ducted exhaust sized to room volume
- Lighting
- Damp-rated recessed + vanity lighting
How it gets built
The sequence matters as much as the selections. Work done out of order is the most common reason remodels run long.
1 — Demolition to studs
Bathrooms come back to framing. It is the only way to see the condition of what is behind the tile, and in older homes there is frequently something worth finding — failed waterproofing, corroded supply lines, or moisture damage in the framing around a shower pan.
2 — Plumbing and electrical rough-in
Relocating a vanity from single to double means moving supply and drain lines and adding circuits for lighting and receptacles. GFCI protection is required throughout. This stage gets inspected before anything is covered.
3 — Waterproofing
The part nobody sees and everything depends on. A continuous membrane system goes behind the tile in the entire wet area, with particular attention to corners, the curb and the drain. Tile and grout are not waterproof — they are the wearing surface over the system that is. Failures in bathroom remodels are almost always waterproofing failures.
4 — Tile
Large-format tile means fewer grout lines, which means less to clean and a calmer-looking room. Running tile to the ceiling in the wet area rather than stopping at shower height costs relatively little more and makes the space read considerably taller.
5 — Glass templating
Frameless glass is templated after the tile is set, because it is cut to the actual opening rather than to the drawing. That means a lead time between tile completion and glass installation — typically a couple of weeks — which we schedule for rather than discover.
6 — Vanity, fixtures and finish
Vanity set and levelled, counter templated, plumbing trim installed, mirrors and lighting hung, then a final walkthrough.
Project Gallery



Design Notes
The garden tub question comes up on nearly every master bath. Be honest about whether you actually use it. If it has not been filled in years, that footprint is worth far more given over to a larger shower — and if resale is the concern, another full bathroom in the house almost always has a tub, which is what buyers and appraisers are looking for.
Ventilation is chronically undersized in Arizona bathrooms. A fan has to be sized to the room's volume and ducted to the exterior — not into the attic, which simply relocates the moisture problem. Under-ventilating a newly tiled bathroom is how you get mildew in grout that is six months old.
Drawers beat doors under a vanity. Base cabinets with doors turn into a place where things go to be forgotten at the back. Drawers make the entire depth accessible, and it is the single upgrade homeowners mention most often afterward.